Today, ENTSO-E publishes its report “Accelerating Grid Connections: What TSOs Propose”. Drawing on the experience of Europe’s transmission system operators (TSOs), the report sets out practical measures to help projects connect sooner, make better use of available grid capacity and provide greater clarity to applicants.  

The report assesses the measures proposed in the European Commission’s Guidance on efficient and timely grid connections (C/2025/6703). It also aims to inform the ongoing work on the Electrification Action Plan and the proposal to future-proof electricity bills, which introduces new rules on managing connection requests where grid capacity is scarce.  

As electrification in Europe progresses, demand for electricity is growing and more renewable energy sources need to connect tothe grid. In many countries, connection requests exceed the volumes anticipated in network development plans. Beyond the availability of grid capacity, delays also arise from complex permitting procedures, spatial planning, supply chain constraints and the time needed to build or reinforce electricity networks. 

ENTSO-E’s report highlights practical solutions already used in several countries to manage growing connection requests more effectively. These include:  

  • Clear entry requirements: ensuring that applicants meet defined criteria before entering the connection queue. 
  • Progress milestones: requiring projects to demonstrate progress at key stages of the connection process. 
  • Release of unused capacity: creating rules to prevent stalled projects from holding up others.  
  • Flexible connection agreements: allowing projects to connect earlier even where grid capacity is initially limited. 

The report also calls for closer coordination between connection procedures and long-term grid planning, alongside regulatory frameworks that enable investment ahead of future needs where demand signals are credible.  

Any new rules should support an efficient and predictable connection process. Information on available grid capacity should also provide applicants with a clear understanding of the technical conditions and uncertainties involved. 

The objective is to accelerate connections while maintaining the secure and reliable electricity supply that consumers depend on. Effective management of grid connection queues can help unlock renewable generation, storage, and new electricity demand, supporting delivery of Europe’s energy transition.  